Weybridge Gardens has entered its final construction phase, with overall site progress now at 95%. The development is in the last round of finishing works, bringing every area of the project closer to completion.
Structural work is now complete, with concrete and masonry wrapped up months ago, forming a strong backbone for today’s refined finishes. Metal installations are nearly done at 98%, while woodwork, including cabinetry, wall panels, and joinery, has advanced to 90%. Doors and windows continue to move forward with precision, now at 97%.
Interior finishes such as tiling, paintwork, and decorative features are progressing steadily, with 90% delivered. Accessories and fixtures are almost complete at 98%, while external works, including landscaping, paving, and façade enhancements, have reached 93%.
With only a small portion of work left, focus has shifted from construction to perfection. Weybridge Gardens is on the verge of handover, promising homeowners a world-class community, completed on schedule or even ahead.
Weybridge Gardens has entered its final construction phase, with overall site progress now at 95%. The development is in the last round of finishing works, bringing every area of the project closer to completion.
Structural work is now complete, with concrete and masonry wrapped up months ago, forming a strong backbone for today’s refined finishes. Metal installations are nearly done at 98%, while woodwork, including cabinetry, wall panels, and joinery, has advanced to 90%. Doors and windows continue to move forward with precision, now at 97%.
Interior finishes such as tiling, paintwork, and decorative features are progressing steadily, with 90% delivered. Accessories and fixtures are almost complete at 98%, while external works, including landscaping, paving, and façade enhancements, have reached 93%.
With only a small portion of work left, focus has shifted from construction to perfection. Weybridge Gardens is on the verge of handover, promising homeowners a world-class community, completed on schedule or even ahead.
We are delighted to announce that Hadley Heights has officially received its 100% Building Completion Certificate, signifying the successful and ahead-of-schedule completion of all construction works.
True to our commitment to excellence, our team is now in the final stages of preparing the development for handover. Utility connections for DEWA, chiller and gas are well underway and nearing completion, ensuring that every aspect of the building meets the highest standards of comfort and functionality.
Built with precision and care, Hadley Heights reflects premium British quality in every detail from construction to finishing. With final commissioning progressing smoothly, the handover is just around the corner.
We look forward to welcoming our esteemed homeowners and investors very soon to Hadley Heights, where quality living begins.
We are delighted to announce that Hadley Heights has officially received its 100% Building Completion Certificate, signifying the successful and ahead-of-schedule completion of all construction works.
True to our commitment to excellence, our team is now in the final stages of preparing the development for handover. Utility connections for DEWA, chiller and gas are well underway and nearing completion, ensuring that every aspect of the building meets the highest standards of comfort and functionality.
Built with precision and care, Hadley Heights reflects premium British quality in every detail from construction to finishing. With final commissioning progressing smoothly, the handover is just around the corner.
We look forward to welcoming our esteemed homeowners and investors very soon to Hadley Heights, where quality living begins.
Construction at Weybridge Gardens 2 is off to a strong start, with early-stage works progressing efficiently and our dedicated teams working tirelessly on-site to maintain momentum and precision.
General requirements have reached 25% completion, while site works are pushing ahead at 75%, laying the essential groundwork for upcoming structural activities.
Concrete works are now underway, with foundation pouring in progress and structural elements beginning to rise, currently at 10% completion. Mechanical and electrical installations have commenced in parallel, with early-stage progress at 6% and 5% respectively.
External works have also begun, with preliminary ground preparation marking 2% completion.
Our teams are working around the clock to ensure seamless coordination across all disciplines. Every task is being executed with attention to detail and a clear focus on delivering quality from the ground up.
As we prepare to enter the next stage of construction, structural works will accelerate significantly. The project remains firmly on track, driven by our commitment to deliver a high-calibre residential development with the consistency and care our homeowners expect.
Construction at Weybridge Gardens 2 is off to a strong start, with early-stage works progressing efficiently and our dedicated teams working tirelessly on-site to maintain momentum and precision.
General requirements have reached 25% completion, while site works are pushing ahead at 75%, laying the essential groundwork for upcoming structural activities.
Concrete works are now underway, with foundation pouring in progress and structural elements beginning to rise, currently at 10% completion. Mechanical and electrical installations have commenced in parallel, with early-stage progress at 6% and 5% respectively.
External works have also begun, with preliminary ground preparation marking 2% completion.
Our teams are working around the clock to ensure seamless coordination across all disciplines. Every task is being executed with attention to detail and a clear focus on delivering quality from the ground up.
As we prepare to enter the next stage of construction, structural works will accelerate significantly. The project remains firmly on track, driven by our commitment to deliver a high-calibre residential development with the consistency and care our homeowners expect.
Owning a home is a keystone of wealth… both financial affluence and emotional security.
Suze Orman| Cookie | Duration | Description |
|---|---|---|
| cookielawinfo-checkbox-analytics | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookie is used to store the user consent for the cookies in the category "Analytics". |
| cookielawinfo-checkbox-functional | 11 months | The cookie is set by GDPR cookie consent to record the user consent for the cookies in the category "Functional". |
| cookielawinfo-checkbox-necessary | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookies is used to store the user consent for the cookies in the category "Necessary". |
| cookielawinfo-checkbox-others | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookie is used to store the user consent for the cookies in the category "Other. |
| cookielawinfo-checkbox-performance | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookie is used to store the user consent for the cookies in the category "Performance". |
| viewed_cookie_policy | 11 months | The cookie is set by the GDPR Cookie Consent plugin and is used to store whether or not user has consented to the use of cookies. It does not store any personal data. |